# Yoyos 50
# Prototypes 10

Assumptions
 
1 hour per injection molded part (optimize)
1 hour per thermoformed part (optimize)
1 hour per ring injection molded part to run 100 parts
2 hours for body injection molded part to run 100 parts
2.5 hours for thermoformed part to run 100 parts

Component Time/ea (min) Total Time (min)
002-005 (Thermoform) 13.5 216
# parts 1  
Cavity Mold 6 6
Process Optimization 6 60
Production Run 1.5 150
     
005-002 (Ring) 16.6 130
# parts 2  
Core Mold 4 4
Cavity Mold 6 6
Process Optimization 6 60
Production Run 0.6 60
     
001-002 (Body) 24.2 197
# parts 2  
Core Mold 15 15
Cavity Mold 2 2
Process Optimization 6 60
Production Run 1.2 120
     
003-003 (Spinner) 92.6 260
# parts 2  
Core Mold  20 20
Cavity Mold  60 60
Process Optimization 12 120
Production Run 0.6 60
 
TOTAL 803